Gas processing plant at Kashagan planned to be launched in Q3 2027

Construction of the gas processing plant at Kashagan continues, with commissioning scheduled for Q3 2027.

Gas processing plant at Kashagan planned to be launched in Q3 2027

The head of QazaqGaz, Alibek Zhamaouov, reported to the president on the progress of the work, Akorda reports.

The gist in brief

  • The plant at Kashagan is designed for 1 billion m³ of gas per year, with commissioning scheduled for the third quarter of 2027.
  • The second plant at Kashagan with a capacity of 2.5 billion m³ per year and the plant at Karachaganak with 5 billion m³ per year: contractors for them have been selected.
  • The second line of the Beineu - Bozoy - Shymkent gas pipeline, about 1,450 km long: design, procurement and construction work have begun.
  • The launch date of the first plant has been postponed several times.

What is being built at Kashagan

The plant is being built to process Kashagan's sour gas. The plant's capacity is up to 1 billion m³ of raw gas per year. According to QazaqGaz, as of July 2026 readiness stood at 61.4%. In October, at a meeting between Prime Minister Olzhas Bektenov and the heads of the Qatari holding company Power International Holding, the Ministry of Energy reported that construction and installation work is underway at the plant and that the delivery of the main equipment is almost complete. The project cost was estimated at approximately $1 billion (2024 estimate).

How the deadlines shifted

The launch of the plant has been postponed more than once: first 2025 was named, then mid-2026 and the end of 2026. Now the deadline is the third quarter of 2027.

What else is being built in the gas industry

The second plant at Kashagan is to process 2.5 billion m³ of gas per year. According to the Ministry of Energy, a contractor has been selected for it to handle design, procurement and construction, and the project is planned to be completed by 2030. Cost estimates in 2024 stood at $2-2.5 billion. Another plant with a capacity of 5 billion m³ per year is planned to be built at Karachaganak.

Gas from these fields needs to be delivered to consumers. The first line of the Beineu - Bozoy - Shymkent gas pipeline has been operating at full capacity since 2015 and carries about 15 billion m³ per year. The second line, about 1,450 km long (the first stage is planned to be completed in 2027, the second in 2029), will make it possible to supply gas to the southern regions, as well as to the center and north of the country.

What else was reported to the president

Zhamaouov also reported that QazaqGaz is fully prepared for the 2026-2027 heating season. According to him, geological exploration is underway at the Shalkar, Saralzhyn, Maldybay, Severny-1, Severny-2, Akkuduk and Pridorozhnoye areas. The company continues the phased replacement of more than 1.3 million gas meters with smart meters. Among the plans are the gasification of Kokshetau and Petropavlovsk, a small-scale plant for the production of liquefied natural gas in Rudny with a capacity of 50 thousand tons per year, and the start of construction of a fourth underground gas storage facility.

What else is happening with Kashagan and gas in Kazakhstan

The level of gasification in the country has grown from 43% in 2016 to more than 64% by the beginning of 2026, and the president has instructed that it be brought to 80%. The North Kazakhstan region, where Petropavlovsk is located, has not yet been gasified: a main gas pipeline is being built for it from KS-14 in the Aktobe region to Kostanay.

There is ongoing dispute around the field itself. In July, the Ministry of Justice began enforced recovery of about 2.36 trillion tenge (approximately $5 billion) from the Kashagan operator: the fine is related to exceeding sulfur storage volumes, and the operator cites an arbitration injunction. In addition, according to Bloomberg, the arbitration court did not accept part of Kazakhstan's claims against the consortium, amounting to about $12 billion in expenses for 2011-2015, considering them to have been filed late. This has not been officially confirmed.

Author's conclusion

The Kashagan plant will be the first in a series of three gas processing projects, but its launch has already been postponed several times, from 2025 to the third quarter of 2027. Therefore, the main question is whether the contractors will meet the new deadline: in July readiness stood at 61.4%.