Karachaganak gas processing plant to be built by consortium with Hyundai Engineering
QazaqGaz has signed an EPC contract for the design, procurement and construction of a new gas processing plant at the Karachaganak field in western Kazakhstan.
The plant's capacity will be 5 billion cubic meters of gas per year; the contract was signed on November 12 during a working trip by QazaqGaz Management Board Chairman Alibek Zhamaouov to South Korea, QazaqGaz reports.
The gist in brief
- The customer is QazaqGaz Processing LLP, a subsidiary of QazaqGaz; the contractor is a consortium of South Korea's Hyundai Engineering and SICIM Kazakhstan LLP.
- The plant's production capacity will be 5 billion cubic meters of gas per year.
- The plant will produce commercial gas, liquefied petroleum gas and sulfur for the domestic market.
- The cost is not stated in the contract announcement: the regional akim in August cited 1.7 trillion tenge, while an expert estimates the project at about $6 billion.
What was signed
The contract covers design, equipment procurement and construction of the plant. It is needed to significantly increase processing of raw Karachaganak gas and to supply the domestic market with commercial gas, liquefied petroleum gas and sulfur. The project is being implemented on the president's instructions and is expected to strengthen the country's energy security and boost the economic potential of the West Kazakhstan region.
Why the project took so long
Initially the plant was to be built under a production sharing agreement involving Shell, Eni, Chevron, LUKOIL and KazMunayGas, Forbes.kz writes. In 2023, Shell and Eni did not take a final investment decision. In 2025, an increase in the budget from $3.5 billion to $6 billion and a postponement of the launch from 2028 to 2030 were discussed, after which Kazakhstan decided to consider transferring the project to national companies. In April 2026, QazaqGaz was named the sole operator, and on September 15 the parties signed an implementation agreement.
How much it will cost
The total cost of the contract is not stated in the signing announcement. The akim of the West Kazakhstan region, Nariman Turegaliyev, reported to the president on August 13 that the plant would be built for 1.7 trillion tenge, with the Ministry of Energy expecting commissioning by 2030. Expert Nurlan Zhumagulov, according to Forbes.kz, estimates the project cost at about $6 billion.
What is happening with the gas industry of Kazakhstan and Central Asia
Shortly before Karachaganak, on November 6, QazaqGaz Processing signed in China a contract for a second gas processing plant at Kashagan with a capacity of up to 2.5 billion cubic meters of raw gas per year, to be built by a consortium of Chinese and Kazakh companies. Gas consumption in the five Central Asian countries in 2025 reached 119.6 billion cubic meters, 76% more than in 2015, while the region's exports nearly halved, from 89.6 to 47.4 billion cubic meters, with Kazakhstan's exports falling from 20.11 to 4.77 billion cubic meters. Kazakh expert Askar Ismailov estimated the idea of a gas ring for Central Asia that would unite the gas transmission systems of the five countries at about $5 billion.
Author's conclusion
The contract was signed after several years during which the project moved from an agreement with international partners to a national company. But the key parameters remain open so far: the signing announcement contains neither the cost nor the start date of construction, and the estimates of 1.7 trillion tenge and $6 billion are cited in different currencies and by different people. The official contract price and the construction start date will be the real benchmarks.