The issue of localizing the production of power equipment was raised by a deputy of the Kurultai
Kurultai MP Baktybek Bibaev proposed creating a Center for Energy Engineering Development and fixing localization requirements in contracts for major energy projects.
According to Bibayev, the state and corporations are directing hundreds of billions of tenge toward the modernization and construction of CHPPs and state district power plants, but the projects are still oriented toward imported turbines and generators. The request was sent to First Deputy Prime Minister Nurlybek Nalibayev, reports Zakon.kz.
The gist in brief
- The deputy believes that money for the energy sector, which comes through tariffs and direct financing, mostly goes to foreign equipment.
- Example: the Karaganda Turbomechanical Plant manufactured a steam turbine with a capacity of 60 MW this year, but the customer chose a cheaper Chinese analogue.
- The deputy proposes creating a Center for the Development of Power Engineering, enshrining localization requirements in contracts, and supporting domestic manufacturers.
- There is no response from government agencies in the publications.
What the deputy is saying
Bibayev recalls that he raised this issue back in 2023. According to him, the situation has not changed: modernization and construction projects for energy capacities are oriented toward supplies of turbines, generators, and other equipment from abroad. At the same time, the country has a production base and engineering personnel.
He gives an example: the Karaganda Turbomechanical Plant developed and manufactured a 60 MW steam turbine on order, after which the customer preferred a Chinese analogue that was cheaper. Comparing a single unit with serial foreign products, according to the deputy, is incorrect: with stable orders and long-term contracts, the cost is distributed over the production run.
Demand for energy, as noted in the appeal, will continue to grow due to the construction of new power plants, data centers, the development of artificial intelligence, and the digitalization of the economy.
What the deputy proposes
There are five proposals:
- consider creating a Center for the Development of Power Engineering with the participation of government agencies, QazIndustry, Samruk-Energy, energy companies, and major subsoil users of the mining and metallurgical complex;
- determine the need for imported equipment, assess localization opportunities, and compile a list of priority industries;
- develop mechanisms to incentivize cooperation with foreign suppliers: transfer of technical documentation, localization requirements, joint production;
- consider enshrining such requirements in contracts for major energy projects;
- support enterprises that produce turbines, generators, boiler units, compressors, and other complex equipment.
The deputies also ask to organize testing of equipment in real conditions, its conformity confirmation, and the transition to serial production.
What example the deputy cites
He calls the International Center for the Development of Oil and Gas Engineering, created in 2020 by TCO, Karachaganak, and NCOC, a model. According to the deputy, within the framework of its work, 10 localization projects have been implemented and about 20 billion tenge in investments has been attracted.
What this means for Kazakhstan
Equipment for the energy sector is needed in large volumes. In the energy sector, 24 investment agreements for 3.8 GW are being implemented, and by 2035 they plan to add at least 8.4 GW of renewable capacity. The Development Bank of Kazakhstan approved about 54.5 billion tenge for the first stage of a 1 GW project: 60 MW of solar stations for Kazatomprom and 185 MW for KEGOC.
Author's conclusion
The deputy's main argument is the difference between a single unit and a serial product: the turbine was made for a single order and compared with Chinese serial products. The proposals so far remain a request: there are no deadlines or response from government agencies.
Comments ()